The project will consist of the construction of a spring box ; conduction line of 5.2 km; a 5 cubic meter storage tank;and repairs of an existing storage tank.
Narrative
The Pulay Water Project is complete with all elements of the project installed and functioning. The project is two weeks ahead of schedule with the finish. In consultation with the village water committee and Rahesh the plan is to enclose another spring site that the village has recently purchased so as to make this water available for future needs. The village has been very cooperative and raised about Q35,000 ($5,000) during the project and with these funds made a number of improvements to their distribution system the the houses in the village. We anticipate being finished by the end of Jan. with the project.
-
Lynn Roberts of Agua Para La Salud (APLS)
- confidential
Implementation Status: in_progress Thu 15 Jan 2009, Over 16 Years agoPulay Water System
The project was finished two weeks early with all of the original elements of the project completed and functioning. In consultation with the village water committee and Rahesh the plan is to capture another spring site and repair a large public water station. The project should be finished by the end of Jan.
- Impact Assessment (M&E) Phase Project completed on 15 Jan, 2009 Implementation Phase
- Implementation Phase Project started on 20 Oct, 2008 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
The project will consist of the construction of a spring box ; conduction line of 5.2 km; a 5 cubic meter storage tank;and repairs of an existing storage tank.
Narrative
The Pulay Water Project is complete with all elements of the project installed and functioning. The project is two weeks ahead of schedule with the finish. In consultation with the village water committee and Rahesh the plan is to enclose another spring site that the village has recently purchased so as to make this water available for future needs. The village has been very cooperative and raised about Q35,000 ($5,000) during the project and with these funds made a number of improvements to their distribution system the the houses in the village. We anticipate being finished by the end of Jan. with the project.
Sustainability
Creating and measuring long-term impact
We are currently working with the village to develop a maintenance program including the new facilities.
Other Issues
Unusual and unexpected issues faced during project execution
A second phase of this project is planned provided funds can be found. During the project a study was done of the distribution system to the houses. Thefindings indicated that about 90 families were not connected to the water system. We have developed a plan and design to renovate the entire water distribution system to provide sufficient flow to all the houses for a period of 20 years utilizing the old and new springs on line in the village.
Learnings
Knowledge of project and process for sharing
See final report
Impact
People Getting Safe Drinking Water: 2100
Our original submission indicated that there were about 250 families in the village. During the project the village water committee indicated that they had only given us the number of families connected to the system. In reality many young families living with parents and families not connect to the system raised the total number of families to about 350.
People Getting Other Benefits: 2100
Health and higiene education was carried out housey house and in public meetings.
Maintenance/Operating Costs Annual, in US$: $300
Creating and measuring long-term impact
We are currently working with the village to develop a maintenance program including the new facilities.
Funding
- funded:
- $24,761
- Final Cost:
- $26,884