This site #PW240, is in Medyermat village of Hingara panchayat of Chakdah block of Nadia district. The land is donated by Partho Ray. Village meeting pending.
-
Shikha Majumdar of Project Well
- confidential
- SMS
Implementation Status: completed Thu 16 Jan 2014, Over 11 Years agothis well is used by 23 families 103 people .500ml theolin war given .
-
Shikha Majumdar of Project Well
- confidential
- SMS
Implementation Status: completed Sat 30 Nov 2013, Over 11 Years agogive the hand over lettar packet. good water 22 families k cooking and drinking.
-
Shikha Majumdar of Project Well
- confidential
- SMS
Implementation Status: completed Tue 20 Aug 2013, Almost 12 Years agorepairing ofcheck value washer. heelth meeting is ok 12 families36 people.
-
Shikha Majumdar of Project Well
- confidential
- SMS
Implementation Status: completed Mon 21 Jan 2013, Over 12 Years agoSARBEY AND GIVE THE THOLIN 500GM
-
Ranajit Bala of Project Well
- confidential
- SMS
Implementation Status: completed Sat 29 Dec 2012, Over 12 Years agoWATER IS GOOD.22 FAMILIES 90 PEOPLE. DRINKING & COOKING
-
Ranajit Bala of Project Well
- confidential
- SMS
Implementation Status: completed Fri 09 Nov 2012, Over 12 Years agothis well is used by 21 families 109 people.
- Impact Assessment (M&E) Phase Project completed on 31 Oct, 2012 Implementation Phase
-
Meera Hira-Smith of Project Well
- confidential
Implementation Status: completed Sat 13 Oct 2012, Over 12 Years agoConstruction is complete
People are using the water. And please see the final report document uploaded as pdf here> http://peerwater.org/en/projects/740.
Pictures will be uploaded by this week.
- Implementation Phase Project started on 2 Apr, 2012 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
This site #PW240, is in Medyermat village of Hingara panchayat of Chakdah block of Nadia district. The land is donated by Partho Ray. Village meeting pending.
MetriX Summary
-
PW240: Number of families (1)
-
PW240: Number of users (1)
-
PW240: Column of Water(ft) (1)
-
PW240: Theoline (Chlorine) Supplied in ml (1)
Impact
People Getting Safe Drinking Water: 109
Registers will be created as soon as the community starts using the water from this bore-dugwell
Maintenance/Operating Costs Annual, in US$: $40
Creating and measuring long-term impact
Implementer: Project Well & Aqua Welfare Society
Aqua Welfare Society (AWS) is the partner NGO of Project Well.
Funding
- funded:
- $1,246
Plan/Proposal
MetriX Summary
-
PW240: Number of families (1)
-
PW240: Number of users (1)
-
PW240: Column of Water(ft) (1)
-
PW240: Theoline (Chlorine) Supplied in ml (1)