Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
MetriX Summary
-
PW236: Number of Families (3)
-
PW236: Number of Users (3)
-
PW236: Column of Water (ft) (3)
-
PW236: Theoline (Chlorine) supplied in ml (4)
show allDocuments
Narrative
New site in North 24 Parganas in the Baduria Block. This bore-dugwell #PW236 is in the Soyadpur village of Bagjala Panchayat and the land is donated by Noor Islam.
-
Meera Hira-Smith of Project Well
- confidential
Implementation Status: completed Fri 27 Dec 2013, Over 11 Years agoField Visit: This well is being used now after the 27 cubic feet soak tank to accumulate water is constructed.
Field Visit: This well is being used now after the 27 cubic feet soak tank to accumulate water is constructed at a distance of six feet from the well. The water is drained through a pipe.
-
Farida Bibi of Project Well
- confidential
- SMS
Implementation Status: completed Thu 01 Aug 2013, Almost 12 Years agopw236 we are doing health meeting Total 16-M10 F3-C3
- Impact Assessment (M&E) Phase Project completed on 31 Oct, 2012 Implementation Phase
-
Meera Hira-Smith of Project Well
- confidential
Implementation Status: in_progress Mon 21 May 2012, About 13 Years agoPilot Test
Pilot test was done to check the depth of sand layer. The sand layer was located at the depth of 7 feet. Village meeting is scheduled.
- Implementation Phase Project started on 1 Nov, 2011 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
New site in North 24 Parganas in the Baduria Block. This bore-dugwell #PW236 is in the Soyadpur village of Bagjala Panchayat and the land is donated by Noor Islam.
MetriX Summary
-
PW236: Number of Families (3)
-
PW236: Number of Users (3)
-
PW236: Column of Water (ft) (3)
-
PW236: Theoline (Chlorine) supplied in ml (4)
show allDocuments
Impact
People Getting Safe Drinking Water: 40
Maintenance/Operating Costs Annual, in US$: $40
Creating and measuring long-term impact
Implementer: Project Well & Aqua Welfare Society
Aqua Welfare Society (AWS) is the partner NGO of Project Well.
Funding
- funded:
- $1,073