Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
New site in North 24 Parganas in the Baduria Block. This bore-dugwell #PW234 is in the Charaktala village of Bagjala Panchayat and the land is in front of the Charaktala Temple. The site selection was facilitated by Mr. Samsur Haque, who is a member of the Panchayet. Village meeting will be held on 22nd of May and the site is finalized.
-
Farida Bibi of Project Well
- confidential
- SMS
Implementation Status: completed Fri 03 Jan 2014, Over 11 Years agoHealth meeting has been finished. Total- 26.
-
Laltu Mirza of Project Well
- confidential
- SMS
Implementation Status: completed Fri 03 Jan 2014, Over 11 Years agorepair today.
-
Meera Hira-Smith of Project Well
- confidential
Implementation Status: completed_partial Thu 26 Dec 2013, Over 11 Years agoField Visit: Not used. community is not well informed maintenance of the bi-tech well. After repair in February projector program will be held.
Not used. community is not informed well about the bi-tech well. After repair in February projector program will be held. Due to organic smell at the initial stage of construction in 2012 and not pumping the water the community and the visitors of the mosque never felt encouraged to use the well. We spoke to local young men who were complaining about the quality of water being smelly. They were explained about operation after construction that was done that is it is essential to pump the water at the initial stage to get clear water. Since nobody pumped the stagnant water produced strong organic smell after few days that discouraged the people. In February this well will be cleaned followed by village meeting on maintenance and also projector program has been scheduled.
- Impact Assessment (M&E) Phase Project completed on 31 Oct, 2012 Implementation Phase
-
Meera Hira-Smith of Project Well
- confidential
Implementation Status: in_progress Sat 26 May 2012, About 13 Years agoVillage meeting
village meeting was held on 22nd and the community members are excited about this safe source of drinking water.
-
Meera Hira-Smith of Project Well
- confidential
Implementation Status: completed Mon 21 May 2012, About 13 Years agoPilot Test
Pilot test was completed and sand was located at a depth of 12 feet. the site is confirmed for village meeting.
- Implementation Phase Project started on 1 Nov, 2011 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
New site in North 24 Parganas in the Baduria Block. This bore-dugwell #PW234 is in the Charaktala village of Bagjala Panchayat and the land is in front of the Charaktala Temple. The site selection was facilitated by Mr. Samsur Haque, who is a member of the Panchayet. Village meeting will be held on 22nd of May and the site is finalized.
Impact
People Getting Safe Drinking Water: 40
Maintenance/Operating Costs Annual, in US$: $40
Creating and measuring long-term impact
Implementer: Project Well & Aqua Welfare Society
Aqua Welfare Society (AWS) is the partner NGO of Project Well.
Funding
- funded:
- $1,073