Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
Digging and boring at this site is complete. The land is donated by Monikuntal of 2nd Colonyof Swarupnagar block. Masonry job is going on. All these 10 sites are in the Gobindopur Panchayet.
____________________________
Site selection is ongoing that includes community (village) meeting, recording of the geocode of the site proposed by the community.
-
Farida Bibi of Project Well
- confidential
- SMS
Implementation Status: completed Tue 24 Sep 2013, Over 11 Years agowe have come here to test the low tech home made filter today. it was successful. the water passed through was clear, removed turbidity and iron.
-
Laltu Mirza of Project Well
- confidential
- SMS
Implementation Status: completed Fri 06 Sep 2013, Almost 12 Years agoset checkvalve today.
-
Farida Bibi of Project Well
- confidential
- SMS
Implementation Status: completed Fri 24 May 2013, About 12 Years agopeople are not using because the water turbid
-
Suparna Mondol of Project Well
- confidential
- SMS
Implementation Status: completed Fri 07 Dec 2012, Over 12 Years agoProjector program is ok. 42 people present .
- Impact Assessment (M&E) Phase Project completed on 31 Oct, 2012 Implementation Phase
-
Biswajit Karmakar of Project Well
- confidential
Implementation Status: completed Wed 04 Jul 2012, Almost 13 Years ago - Implementation Phase Project started on 1 Nov, 2011 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
Digging and boring at this site is complete. The land is donated by Monikuntal of 2nd Colonyof Swarupnagar block. Masonry job is going on. All these 10 sites are in the Gobindopur Panchayet.
____________________________
Site selection is ongoing that includes community (village) meeting, recording of the geocode of the site proposed by the community.
Other Issues
Unusual and unexpected issues faced during project execution
The large diameter (10”) pipes for 25 bore dugwells have arrived within 3 weeks after placing the order. The construction team is engaged in conducting site selection procedures while the awareness team is continuing with awareness programs in schools and communities in the areas where dugwells are in operation.
Impact
People Getting Safe Drinking Water: 40
Registers will be created as soon as the community starts using the water from this bore-dugwell.
Maintenance/Operating Costs Annual, in US$: $40
Creating and measuring long-term impact
Implementer: Project Well & Aqua Welfare Society
Aqua Welfare Society (AWS) is the partner NGO of Project Well.
Funding
- funded:
- $1,073