The new site for borewell #PW209 is in Hyderpur village of Baduria block of N 24 Parganas district. This land is donated by Nur Mohammad to the community to construct the bore-dugwell.
_______________________________________

31st December: Boring is complete. Tried to do digging at this site but due to the water table being still high digging is postponed that will be done in the second week of January 2012.
_______________________
"After cancellation of sites and with the onset of the monsoon work was postponed. Expected to be completed by end of December.
____________________
CANCELLED SITE AFTER PILOT TEST. "

____________________
CANCELLED SITE AFTER PILOT TEST.

This site #PW203, is in the premises of the Kali Mandir of Bajetpur village of Baduria block of N 24 Parganas district.

This year there is a delay in the construction due to the following reasons:
1. during april and may no village meetings could be held because of assembly election in the state election;
2. many sites were selected and village meetings were held several months before the construction. Many sites were cancelled because of pipelines that the local panchayet came to know about later. In fact sites in two blocks, Haringhata and Bashirhat have been replaced by sites in Baduria and Swarupnagar.
3. During pilot tests due to non availability of water bearing sand layer and family or neigborly disputes by now 22 sites been cancelled.
4. At every new site village meetings are being held that leads to delay too.