Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
This site #PW174,Goalbari paschim para village of Chakdah block of Nadia district. Rabindra Biswas donate d the site for the community.
-
Suparna Mondol of Project Well
- confidential
- SMS
Implementation Status: completed Tue 10 Dec 2013, Over 11 Years agoHealth meeting has been finished. F-10, Ch-1.
-
Shikha Majumdar of Project Well
- confidential
- SMS
Implementation Status: completed Thu 22 Aug 2013, Almost 12 Years agorepairing of checkvalve.4 fit water gave 500 ml theoline.
-
Shikha Majumdar of Project Well
- confidential
- SMS
Implementation Status: completed Thu 01 Aug 2013, Almost 12 Years agohelth meeting is ok people10 me2 fe7chi 1.
-
Ranajit Bala of Project Well
- confidential
- SMS
Implementation Status: completed Thu 25 Jul 2013, Almost 12 Years agopw-174 repairing of plunger of handpump
-
Laltu Mirza of Project Well
- confidential
- SMS
Implementation Status: completed Mon 10 Jun 2013, About 12 Years agohas been washed.
-
Shikha Majumdar of Project Well
- confidential
- SMS
Implementation Status: completed Mon 31 Dec 2012, Over 12 Years agoNot using.dodeging.
- Impact Assessment (M&E) Phase Project completed on 31 Jul, 2011 Implementation Phase
- Implementation Phase Project started on 1 Oct, 2010 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
This site #PW174,Goalbari paschim para village of Chakdah block of Nadia district. Rabindra Biswas donate d the site for the community.
Impact
People Getting Safe Drinking Water: 40
It is estimated that 40 people will obtain water from source. Registers will be created as soon as the community starts using the water from this bore-dugwell.
Maintenance/Operating Costs Annual, in US$: $40
Creating and measuring long-term impact
Implementer: Project Well & Aqua Welfare Society
Aqua Welfare Society, AWS, is the partner NGO of Project Well. Their office is based in the North 24 Parganas. The 7 honorary board members are located in Kolkata. There were only 5 field workers who were interacting with the villagers and beneficiaries, training the users on maintenance of the dugwells, organizing village meetings and health meetings. This year four more field workers including a management trainee have been contracted due to expansion of the program to other districts like Nadia and Murshidabad. A technical advisor of AWS is based in Kolkata who visits the village occasionally and one awareness programmer who is Aqua Welfare Society, AWS, is the partner NGO of Project Well. in charge of awareness programs in the communities and educational institutions. There is an accountant and also a data entry person on part time basis.
Funding
- funded:
- $1,160