Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
MetriX Summary
-
PW167: Number of Families (3)
-
PW167: Number of Users (2)
-
PW167: Theoline (Chlorine) Supplied in ml (3)
Narrative
This borewell # PW166GPL3, is in the Gopalpur village of Swarupnagar block of North 24 Parganas district. Abu Khurshed Mondol donated the site for the community.
-
Animesh sarkar of Project Well
- confidential
- SMS
Implementation Status: completed_overbudget Thu 10 Jan 2013, Over 12 Years ago.This well is used by 38 families .161 people.Theoline give 400 ml. water 15 ft and water collect for arsenic test.
-
Rudi Dundas
- Visitor
- confidential
Implementation Status: completed Wed 17 Aug 2011, Almost 14 Years agoNovember 23, 2010 - Rudi Dundas and Chris Majors
We were told that 39 families used this well. Until it was installed they had to travel 1km to get drinking water. Water is very good for drinking and cooking. We interviewed the owner, Abu Khurshed and photographed him and some of the villagers.
-
Paramita Guha of Project Well
- confidential
- SMS
Implementation Status: completed Thu 23 Jun 2011, Almost 14 Years agohere water taste is good & more than 10 family uses the water.
- Impact Assessment (M&E) Phase Project completed on 31 Dec, 2010 Implementation Phase
- Implementation Phase Project started on 1 Nov, 2009 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
This borewell # PW166GPL3, is in the Gopalpur village of Swarupnagar block of North 24 Parganas district. Abu Khurshed Mondol donated the site for the community.
MetriX Summary
-
PW167: Number of Families (3)
-
PW167: Number of Users (2)
-
PW167: Theoline (Chlorine) Supplied in ml (3)
Other Issues
Unusual and unexpected issues faced during project execution
The construction of this bore-dugwell is just completed in July 2010. The community has been trained to apply the disinfectant and field workers visits to check its functionality.
Impact
People Impacted: 185
People Getting Safe Drinking Water: 185
According to the register record of July 2011 the total consumers=185; Families=39; Male=89, Female=96, children <5 = 15 and students =76.
_______________________
There are 51 families. Male=85, Female=103 and children=46.
Maintenance/Operating Costs Annual, in US$: $40
Creating and measuring long-term impact
Implementer: Project Well & Aqua Welfare Society
Aqua Welfare Society, AWS, is the partner NGO of Project Well. Their office is based in the North 24 Parganas. The 7 honorary board members are located in Kolkata. There were only 5 field workers who were interacting with the villagers and beneficiaries, training the users on maintenance of the dugwells, organizing village meetings and health meetings. This year four more field workers including a management trainee have been contracted due to expansion of the program to other districts like Nadia and Murshidabad. A technical advisor of AWS is based in Kolkata who visits the village occasionally and one awareness programmer who is in charge of awareness programs in the communities and educational institutions. There is an accountant and also a data entry person on part time basis.
Funding
- funded:
- $800
- Final Cost:
- $1,050
Plan/Proposal
MetriX Summary
-
PW167: Number of Families (3)
-
PW167: Number of Users (2)
-
PW167: Theoline (Chlorine) Supplied in ml (3)