Self-supporting community- based mitigation program that provides Arsenic safe water using modified dugwells along with public education on water related health effects.
MetriX Summary
-
PW333: Number of families (1)
-
PW333: Number of users (1)
-
PW333: Column of Water (ft) (1)
-
PW333: Theoline (Chlorine) Supplied in ml (1)
Narrative
Mithun Parui donated land for the community to construct bi-tech well designed to produce arsenic-free water mainly for cooking and drinking. See 'field notes' for ongoing activities.
- Impact Assessment (M&E) Phase Project completed on 1 Nov, 2015 Implementation Phase
- Implementation Phase Project started on 1 Nov, 2013 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Self-supporting community- based mitigation program that provides Arsenic safe water using modified dugwells along with public education on water related health effects.
Narrative
Mithun Parui donated land for the community to construct bi-tech well designed to produce arsenic-free water mainly for cooking and drinking. See 'field notes' for ongoing activities.
MetriX Summary
-
PW333: Number of families (1)
-
PW333: Number of users (1)
-
PW333: Column of Water (ft) (1)
-
PW333: Theoline (Chlorine) Supplied in ml (1)
Sustainability
Creating and measuring long-term impact
Regular use (and supply) of theoline for water purification and maintaining and repairing hand pump.
Other Issues
Unusual and unexpected issues faced during project execution
PIC DOCS
Impact
Maintenance/Operating Costs Annual, in US$: $2400
Creating and measuring long-term impact
Regular use (and supply) of theoline for water purification and maintaining and repairing hand pump.
Funding
- funded:
- $855
- Community:
- $300
- Final Cost:
- $1,155
Plan/Proposal
MetriX Summary
-
PW333: Number of families (1)
-
PW333: Number of users (1)
-
PW333: Column of Water (ft) (1)
-
PW333: Theoline (Chlorine) Supplied in ml (1)