Build the borehole to help the people in Kachabali village access water. The water point ownership is communal and for domestic use
Narrative
The complete report for the Palissa 1 program (for all 6 borewells) can be seen here.
-
Scott Patterson of International Lifeline Fund
- confidential
Implementation Status: completed Fri 06 Dec 2013, Over 11 Years agoAndrew Makes a Site Visit
While onsite today, I saw that the BH was functionally well. The community was even ahead of schedule in raising funds. It was raining at the site.
- Impact Assessment (M&E) Phase Project completed on 16 Mar, 2013 Implementation Phase
-
Scott Patterson of International Lifeline Fund
- confidential
Implementation Status: completed Fri 15 Mar 2013, Over 12 Years ago -
Scott Patterson of International Lifeline Fund
- confidential
Implementation Status: completed Fri 14 Dec 2012, Over 12 Years agoHand pump installation
Today, the hand pump is installed, the type of the hand pump is UIII Modify
-
Scott Patterson of International Lifeline Fund
- confidential
Implementation Status: completed Thu 13 Dec 2012, Over 12 Years agoYield test done
Today, the yield test is done, the water has constant discharge
-
Scott Patterson of International Lifeline Fund
- confidential
Implementation Status: completed Sat 01 Dec 2012, Over 12 Years agoConstruction complete
Today the construction of Borewell for Nagwere HC III was complete and successful
-
Scott Patterson of International Lifeline Fund
- confidential
Implementation Status: in_progress Fri 16 Nov 2012, Over 12 Years agoSite selection for borewell
Today is the date for site selection for the borewell
-
Scott Patterson of International Lifeline Fund
- confidential
Implementation Status: in_progress Fri 16 Nov 2012, Over 12 Years agoThe 2nd borehole
The second borehole is at Nagwere Health Clinic III, which has a maternity ward and admits patients over night. There are 36 households in immediate village called Kachabale Complex. The HC serves the whole parish. It is located in Petete Sub-County. The borehole was sited on the large health clinic compound and was drilled to 35.1 m total depth with a good flow rate. photo 442 with maternity ward in background with blue metal roof.
- Implementation Phase Project started on 16 Nov, 2012 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Build the borehole to help the people in Kachabali village access water. The water point ownership is communal and for domestic use
Narrative
The complete report for the Palissa 1 program (for all 6 borewells) can be seen here.