Self-supporting community- based mitigation program that provides arsenic safe water using modified bore-dugwell along with public education on water related health effects.
Narrative
This new site #PW271 is in North 24 Parganas in the Swarupnagar block. The name of the donor is khademul mondol of keotali village under the jurisdiction of saguna panchayet.
The previous site was cancelled because of absence of sand layer within 30 feet,
_____________________________
This site #PW271 is in the Maniktala village under the jurisdiction of the Deuli panchayat of Chakda block in the district of North 24 Parganas.. The arsenic concentration of the private tubewell of Kalipawdo Biswas was found to be 0.02 to 0.04 mg/L that was tested on 3 December 2012 with the VisuPAsS Visual Portable Arsenic testing field kit. The construction is supposed to start in mid February 2013.
- Impact Assessment (M&E) Phase Project completed on 30 Nov, 2013 Implementation Phase
-
Farida Bibi of Project Well
- confidential
- SMS
Implementation Status: completed Thu 19 Sep 2013, Over 11 Years agowent for inspection
-
Animesh sarkar of Project Well
- confidential
- SMS
Implementation Status: completed Tue 06 Aug 2013, Almost 12 Years agopw-271.Health meeting held in this bi-tech wel.total-16.m-10.f-3.c-3.
-
Animesh sarkar of Project Well
- confidential
- SMS
Implementation Status: completed Tue 02 Jul 2013, Almost 12 Years agoHealth meeting complete .attend male 5.female 11 .child 2.total 18.present aparna .shilpi and animesh.
-
Suparna Mondol of Project Well
- confidential
- SMS
Implementation Status: completed Tue 02 Jul 2013, Almost 12 Years agoHealth meeting has been finished . M-5,F-11, Ch-2.
-
Animesh sarkar of Project Well
- confidential
- SMS
Implementation Status: completed Tue 02 Jul 2013, Almost 12 Years agoHealth meeting complete .attend male 5.female 11 .child 2.total 18.present aparna .shilpi and animesh.
-
Shilpi Poddar of Project Well
- confidential
- SMS
Implementation Status: completed Mon 10 Jun 2013, About 12 Years agoConstrucetion has been completed.
- Implementation Phase Project started on 1 Dec, 2012 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Self-supporting community- based mitigation program that provides arsenic safe water using modified bore-dugwell along with public education on water related health effects.
Narrative
This new site #PW271 is in North 24 Parganas in the Swarupnagar block. The name of the donor is khademul mondol of keotali village under the jurisdiction of saguna panchayet.
The previous site was cancelled because of absence of sand layer within 30 feet,
_____________________________
This site #PW271 is in the Maniktala village under the jurisdiction of the Deuli panchayat of Chakda block in the district of North 24 Parganas.. The arsenic concentration of the private tubewell of Kalipawdo Biswas was found to be 0.02 to 0.04 mg/L that was tested on 3 December 2012 with the VisuPAsS Visual Portable Arsenic testing field kit. The construction is supposed to start in mid February 2013.
Impact
People Getting Safe Drinking Water: 40
Registers will be created as soon as the community starts using the water from this bore-dugwell.
People Getting Other Benefits: 30
Awareness programs such as village meetings before and after the construction of the well, health meeting and if needed projector program is done during the first year of construction. During this time the villagers are informed and educated on water borne diseases, health effects of arsenic in the drinking water and also educate, both, young and old, mainly women on how practicing proper personal hygiene prevents contagious diseases. At times more than 30 people gather at such meetings.
Maintenance/Operating Costs Annual, in US$: $40
Creating and measuring long-term impact
Implementer: Project Well & Aqua Welfare Society
Aqua Welfare Society (AWS) is the partner NGO of Project Well.
Funding
- funded:
- $1,246