Self-supporting community- based mitigation program that provides arsenic safe water using modified bore-dugwell along with public education on water related health effects.
MetriX Summary
-
PW269: Number of families (2)
-
PW269: Number of users (2)
-
PW269: Column of Water (ft) (2)
-
PW269: Theoline (Chlorine) Supplied in ml (2)
Narrative
This site #PW269. is in the Matikumra village under the jurisdiction of the Chourashi panchayat of Deganga block in the district of North 24 Parganas.. The arsenic concentration of the private tubewell of Aktarul Mondol was found to be 0.02 to 0.04 mg/L that was tested on 11 January 2013 with the VisuPAsS Visual Portable Arsenic testing field kit. The construction is supposed to start in mid February 2013.
- Impact Assessment (M&E) Phase Project completed on 30 Nov, 2013 Implementation Phase
-
Farida Bibi of Project Well
- confidential
- SMS
Implementation Status: completed Thu 11 Jul 2013, Almost 12 Years agowe are doing healthmetting
-
Farida Bibi of Project Well
- confidential
- SMS
Implementation Status: completed Sat 29 Jun 2013, Almost 12 Years agovisited and gave theoline good water 200g theoline
-
Farida Bibi of Project Well
- confidential
- SMS
Implementation Status: completed Wed 05 Jun 2013, About 12 Years agowe well fix marbele plate
-
Meera Hira-Smith of Project Well
- confidential
- SMS
Implementation Status: in_progress Sun 07 Apr 2013, About 12 Years agoconst complete except sponsor plate. Water quality is excellent. Here sand layer is thick, 17 ft. The visiting geologists r very satisfied
-
Farida Bibi of Project Well
- confidential
- SMS
Implementation Status: in_progress Tue 12 Mar 2013, Over 12 Years agodigging is the done in matikomra
-
Meera Hira-Smith of Project Well
- confidential
Implementation Status: in_progress Sat 23 Feb 2013, Over 12 Years agopilot test
This is a new area hence pilot test to locate the sand layer was done. The sand layer was detected at
17 feet. the quality of sand is coarse. - Implementation Phase Project started on 1 Dec, 2012 Preparation Phase
How it Works
Every field note helps building a history of activity at the project site. Every visit should result in a field note, including visits by peers and 3rd parties. Visits can be before implementation, during implementation and during operational state.
If the field note is during the operating phase of the project, then PWX considers the note as a verification note. Verification can show if the current operating state is different from that in the 'final' report and thus draw attention and resources to resolve issues.
Soon PWX AnalytiX will track the number of projects verified and combine that with the amount of time elapsed since 'completion', to summarize monitoring efforts and the sustainability of projects.
Self-supporting community- based mitigation program that provides arsenic safe water using modified bore-dugwell along with public education on water related health effects.
Narrative
This site #PW269. is in the Matikumra village under the jurisdiction of the Chourashi panchayat of Deganga block in the district of North 24 Parganas.. The arsenic concentration of the private tubewell of Aktarul Mondol was found to be 0.02 to 0.04 mg/L that was tested on 11 January 2013 with the VisuPAsS Visual Portable Arsenic testing field kit. The construction is supposed to start in mid February 2013.
MetriX Summary
-
PW269: Number of families (2)
-
PW269: Number of users (2)
-
PW269: Column of Water (ft) (2)
-
PW269: Theoline (Chlorine) Supplied in ml (2)
Impact
Maintenance/Operating Costs Annual, in US$: $40
Creating and measuring long-term impact
Implementer: Project Well & Aqua Welfare Society
Aqua Welfare Society (AWS) is the partner NGO of Project Well.
Funding
- funded:
- $1,246
Plan/Proposal