Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.

Narrative

This site PW230, has been relocated in Baduria block for convenience of construction logistics. This is in the N.hyederpur village of Bagjola panchayet and the land is donated by Haran Mondol.
_______________________________
In Swarupnagar nine sites were cancelled out of eleven hence site selection was moved to Baduria block so that construction can start in the last week of May. Boring started in Badurail on 26th May and Digging is expected to start on 31st. All the field workers are engaged in site selection that includes geocoding, village meetings, pilot testing, boring and digging, All these activities are going on simultaneously.

New site in North 24 Parganas in the Swarupnagar Block. This bore-dugwell #PW230 is in the Pantapara village under the jurisdiction of Gobindopur Panchayet and the exact location of site is not finalized yet.

_______________________
This site #PW230, is the Madyapara village of Ranaghat block in Nadia district. The land was donated by Haran Mondol.This site got cancelled after the village meeting just before the pilot test when the panchayet notified about pipeline water supply to be installed soon in that area.

  • Suparna Mondol of Project Well
    • confidential
    • SMS
    Implementation Status: completed Fri 10 Jan 2014, About 10 Years ago

    Mandra hazer ali smriti vidyapith H.S. Nere by pw-230. projector programme has been finished. St-181, Te-1.

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed Sat 07 Dec 2013, Over 10 Years ago

    there is 20ft of water good water 7families 35people used for drinking and cooking

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed Tue 22 Oct 2013, Over 10 Years ago

    there is 9families 35people good water used for drinking and cooking

  • Farida Bibi of Project Well
    • confidential
    • SMS
    Implementation Status: completed Fri 27 Sep 2013, Over 10 Years ago

    i am giving the handover folder and arsenic report

  • Suparna Mondol of Project Well
    • confidential
    • SMS
    Implementation Status: completed Thu 12 Sep 2013, Over 10 Years ago

    We went to inspect the dugwell no- pw-230.

  • Suparna Mondol of Project Well
    • confidential
    • SMS
    Implementation Status: completed Tue 22 Jan 2013, About 11 Years ago

    Health meeting is ok. F- 10, ch-4.

  • Impact Assessment (M&E) Phase Project completed on 31 Oct, 2012 Implementation Phase
  • Implementation Phase Project started on 1 Nov, 2011 Preparation Phase

Self-supporting community- based mitigation program that provides arsenic safe water using modified dugwells along with public education on water related health effects.

Narrative

This site PW230, has been relocated in Baduria block for convenience of construction logistics. This is in the N.hyederpur village of Bagjola panchayet and the land is donated by Haran Mondol.
_______________________________
In Swarupnagar nine sites were cancelled out of eleven hence site selection was moved to Baduria block so that construction can start in the last week of May. Boring started in Badurail on 26th May and Digging is expected to start on 31st. All the field workers are engaged in site selection that includes geocoding, village meetings, pilot testing, boring and digging, All these activities are going on simultaneously.

New site in North 24 Parganas in the Swarupnagar Block. This bore-dugwell #PW230 is in the Pantapara village under the jurisdiction of Gobindopur Panchayet and the exact location of site is not finalized yet.

_______________________
This site #PW230, is the Madyapara village of Ranaghat block in Nadia district. The land was donated by Haran Mondol.This site got cancelled after the village meeting just before the pilot test when the panchayet notified about pipeline water supply to be installed soon in that area.

Other Issues

Unusual and unexpected issues faced during project execution

The large diameter (10”) pipes for 25 bore dugwells have arrived within 3 weeks after placing the order. The construction team is engaged in conducting site selection procedures while the awareness team is continuing with awareness programs in schools and communities in the areas where dugwells are in operation.

Learnings

Knowledge of project and process for sharing

It is very important that the public health & engineering government offices of West Bengal make the detail map of pipeline with exact names of the villages and paras available to NGO's who are working in the area.

Impact

People Getting Safe Drinking Water: 40

Registers will be created as soon as the community starts using the water from this bore-dugwell.

Maintenance/Operating Costs Annual, in US$: $40

Creating and measuring long-term impact

Implementer: Project Well & Aqua Welfare Society

Aqua Welfare Society (AWS) is the partner NGO of Project Well.

Funding

funded:
$1,073

Plan/Proposal