Helping 500 households from My An Hung B , Lap Vo in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong).

Narrative

Historical Data Imported.

Helping 500 households from My An Hung B , Lap Vo in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong). The following methods were utilized for treatment: . The following chemicals are added:

  • Impact Assessment (M&E) Phase Project completed on 31 Dec, 2010 Implementation Phase
  • Implementation Phase Project started on 1 Jan, 2010 Preparation Phase

Helping 500 households from My An Hung B , Lap Vo in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong).

Narrative

Historical Data Imported.

Helping 500 households from My An Hung B , Lap Vo in Vietnam access drinking water. The system is managed by a local Private Investor (Mekong). The following methods were utilized for treatment: . The following chemicals are added:

Impact

People Impacted: 2500

People Getting Safe Drinking Water: 2500

500.0

Member Specific Project Data

Water Source: G
Project Type: U
Treatment Type:
Chemicals Added:
Length of Pipe System (m): 12959
Comments on Status: Good
Comments on Solutions:
Notes: Good,PE want to extend pipeline sytem (4 km for 150 more HHs connection)
Cost in Local Currency: 1792185619.98454

Funding

funded:
$83,357
Community:
$17,759
Final Cost:
$141,216
$83,357:
GPOBA

Plan/Proposal