| Applicant: Safer Future Youth Development Project | |||
| Status: Approved Accepted | Review Cycle end date: 2004-12-31 | Application ID: 9 | |
Please use this space to discuss elements of the App. You can post questions or comments and they will be seen by the submitter and all reviewers. Anybody can respond to the questions and comments, not just the submitter.
By Rajesh Shah of Blue Planet Run Foundation Posted over 2 years ago
Is this the project funded by BPR in 2004 and needed a small amount to complete? If so, this should be in the 2004 funding cycle (need to create that) and have the total reflect the amounts funded in 2004 and 2005.
By Idriss Kamara of Safer Future Youth Development Project Posted over 2 years ago
no, it was a 2005 project...
maybe I made a mistake entering it as seperate project... phase 1 was the tank at the faith in christ school, phase 2 was this tank. The funds for this tank were requested and received in 2005
Tobias
By Rajesh Shah of Blue Planet Run Foundation Posted over 2 years ago
You are right that the funds were received in 2005. However, for the foundation paperwork we had budgeted phase2 in 2004. Since Safer Future was a new and unknown organization to us, we felt it too risky to fund the entire project.
Also, i believe even phase I went overbudget and we helped out to complete it.
By Idriss Kamara of Safer Future Youth Development Project Posted over 2 years ago
Yes, the project was proposed and also funded in 2004. Phase1 (Faith in Christ) was finished beginning 2005 with the exception of the pump. Phase2 was started in the second half of 2005 and both tanks were finally finished January 2006
By Idriss Kamara of Safer Future Youth Development Project Posted over 2 years ago
Unfortunately there was a typing mistake while entering the data. The total Project Costs as well as the funds applied for should be USD 10,020
| Applicant: | Safer Future Youth Development Project |
| ID: | 9 |
| Status : | Approved Accepted |
| Country: | SIERRA LEONE |
| An amount of 10200 has been funded | |
Fund Used: |
10200 |
Fund Available: |
0 |
| No. of Projects | : | 1 |
| Earliest Date Started | : | 2005-10-28 |
| Latest Date Completed | : | 2006-02-15 |
| Most Recent Update | : | |
| Total Cost | : | 10200 |